Apron West Second Stage


 

Date: 2014 – 2015
Customer: “ADR Engineering S.r.l.”
Subject: Remote Apron for N.3 aircrafts ICAO Category “C” and n.6 aircrafts ICAO Category “E”   – Fiumicino Airport (Rome) – Italy”
  Detailed Project of:

Electrical systems:

  • Electrical Substation 20kV/400V for feeding Apron equipment;
  • Lightning Protection System and Grounding System;
  • Electrical Main Distribution 400V;
  • Panel boards 400V;
  • Electrical Power System;
  • Lighting System;
  • Access Control System;
  • Anti-Intrusion System;
  • CCTV System;
  • Fire Detection System;
  • Service Telephone and Data Network;

Airport Apron Systems:

  • Airfield Lighting Systems;
  • 400Hz ground Power Units including Pits;
  • Preconditioned Aircraft Systems including Pits;
  • Visual Docking Guidance Systems;
  • Apron floodlighting with LED Floodlights;
  • Apron Management System and Control & Monitoring System for Apron equipment;
Position held: Designer
Amount of works: € 8.000.000,00 – Electrical Systems and Airport Apron Systems

I can’t show drawing examples, because the work must be subcontracted yet.